HomeSolutionsNewsCareersAboutLive DemoContact
CASE STUDY — ENERGY & UTILITIES

Legacy PLC Migration &
SCADA Modernisation

How MordeTech migrated a 15-year-old Siemens S5 system to S7-1500 TIA Portal with zero production downtime — replacing aging SCADA panels with a modern web-based HMI and eliminating 3 annual production stoppages worth ₹18 Lakhs per year.

ClientIndustrial Utility Plant
LocationMaharashtra
IndustryEnergy & Utilities — Industrial Processing
Duration22 weeks (migration + commissioning)
CompletedDecember 2024

The Challenge

The client's facility ran on Siemens S5-115U PLCs installed in 2009 — hardware that Siemens discontinued in 2013. Spare parts had become impossible to source, and the last two emergency shutdowns were caused directly by failed S5 CPU modules that took 3 weeks each to replace with used parts sourced from overseas.

The SCADA system was equally dated: proprietary Windows XP-era HMI panels that could no longer connect to the corporate network. Operators had to physically walk to each panel to acknowledge alarms. There was no remote monitoring capability and no data historian for production reporting.

The critical constraint: the facility could not afford a planned shutdown. Any migration had to happen while the plant continued running — 24/7 continuous operation with zero tolerance for interruption.

Our Approach: Parallel-Run Cutover

MordeTech's migration strategy used a parallel-run approach — the new S7-1500 system ran alongside the S5 for 6 weeks in shadow mode, with outputs verified against the live system before any cutover. The strategy had three phases:

  • Phase 1 — Translation (weeks 1–8): Complete manual re-engineering of 14,000 lines of STEP 5 ladder logic into TIA Portal Structured Control Language (SCL) and Function Block Diagram (FBD), preserving all interlocks and safety logic
  • Phase 2 — Parallel Run (weeks 9–14): New S7-1500 rack installed alongside S5, reading all inputs in mirror mode. Outputs from both systems compared every scan cycle — 6 weeks of zero discrepancies required before cutover approval
  • Phase 3 — Cutover & SCADA (weeks 15–22): Saturday night cutover — S5 disconnected, S7-1500 activated in 4 hours. WinCC Unified web HMI deployed simultaneously, replacing all 6 legacy panels with browser-accessible dashboards on industrial tablets

"We were terrified of touching the S5 — it was a black box that nobody fully understood anymore. MordeTech documented everything, ran parallel for six weeks, and the cutover happened on a Saturday night. Monday morning, everything worked. I still can't believe we did it without a single hour of downtime."

— Head of Maintenance, Industrial Utility Plant, Maharashtra (name withheld at client request)

Technical Implementation

  • Complete reverse-engineering of S5 STEP 5 program — 14,000 LOC documented and re-implemented in TIA Portal V18
  • Siemens S7-1515-2 PN CPU with ET 200MP distributed I/O — full replacement for S5-115U rack
  • Custom parallel-run verification tool (Python + OPC-UA) comparing I/O states between old and new systems every 100ms
  • WinCC Unified V20 web-based SCADA — accessible from any browser without client software
  • 6 ruggedised industrial tablets (Siemens IPC277G) replacing fixed HMI panels on shop floor
  • OSIsoft PI System data historian integration — all process variables now logged with 1s resolution
  • PROFIsafe integration for all safety-critical loops (E-stop, pressure relief, temperature trips)
  • Remote access VPN configured for MordeTech support access during 12-month warranty period

Results

  • Zero production downtime during the entire 22-week migration — plant ran continuously throughout
  • 3 annual S5-related production stoppages eliminated — saving ₹18 Lakhs per year in lost output
  • Spare parts dependency eliminated — full S7-1500 spares kit sourced locally for under ₹4 Lakhs
  • Operator alarm response time reduced from 8–12 minutes (walk to panel) to under 30 seconds (tablet notification)
  • Full process data historian now available — enabled shift efficiency reporting for first time in plant's history
  • Remote monitoring capability added — management can view live plant status from any device
  • System life extended by estimated 15+ years with current hardware and software support agreements

More Case Studies

See how MordeTech has delivered measurable results across manufacturing, energy, and process industries.